rtu header image
 

Drying Times

 
 

Under standardised drying conditions of 20c and 65% relative humidity ultraflo hemihydrate liquid floor screed laid at 40mm will dry in 40 days. With the use of under floor heating, a 50mm ultraflo hemihydrate liquid floor screed can be force dried in less than a month.

Under the same drying conditions 100mm of sand cement screed will take 180 days to dry thoroughly.  If surface finishes are fixed to a sand cement screed prior to drying they may subject to cracking as a result of curling or shrinkage.

 

Ultraflo hemihydrate liquid floor screed is not an anhydrite calcium sulphate based liquid screed. Neither is it a concrete screed or sand: cement floor screed. Ultraflo hemihydrate liquid floor screed is delivered to Northern Ireland and ROI.

 
 
 